The Project SPV, Jejuri Hinjewadi Power Transmission, will be developed on a Build-Own-Operate Transfer basis to provide transmission services for 35 years from the Scheduled Commercial Operation Date (SCOD), set 24 months after the SPV transfer.
The project includes construction and commissioning of approximately 115 km of 400 kV double-circuit (D/c) line between Jejuri and Hinjewadi and extension of 400 kV GIS line bays at substations in both locations.
The annual transmission charges are Rs 155.78 crore.
"Prevent unauthorised transactions in your account ; Update your mobile numbers/email IDs with Us. Receive information of your transactions directly from Exchange on your mobile/email at the end of the day” - Issued in the interest of Investors"
"KYC is one time exercise while dealing in securities markets - once KYC is done through a SEBI registered intermediary (broker, DP, Mutual Fund etc.), you need not undergo the same process again when you approach another intermediary."
"No need to issue cheques by investors while subscribing to Equity IPO. Just write the bank account number and sign in the application form to authorise your bank to make payment in case of allotment. No worries for refund as the money remains in investor's account."