G R Infra emerges lowest bidder for Odisha project
17-Mar-23 14:45Hrs IST

The order includes “Construction of tunnel work between Km. 153.0 to 180.0 (Adenigarh - Purunakatak) consisting of Tunnel‐T4, T5, T6 & T7 & allied works of Khurda - Bolangir new rail line project in east coast railway.”

The bid cost of project is Rs 587.59 crore and it will be completed within 24 months from the date of letter of acceptance.

G R Infraprojects is an integrated road engineering, procurement and construction (EPC) company largely focused on road sector. The company has also recently diversified into projects in the railway sector.

The company's consolidated net profit zoomed to Rs 323.65 crore in the quarter ended December 2022 as against Rs 145.48 crore during the previous quarter ended December 2021. Sales rose 12.10% YoY to Rs 2,191.88 crore in Q3 FY23.

The scrip was down 0.68% to Rs 1,022.45 on the BSE.

Powered by Capital Market - Live News

Attention Investor :

"Prevent unauthorised transactions in your account ; Update your mobile numbers/email IDs with Us. Receive information of your transactions directly from Exchange on your mobile/email at the end of the day” - Issued in the interest of Investors"

"KYC is one time exercise while dealing in securities markets - once KYC is done through a SEBI registered intermediary (broker, DP, Mutual Fund etc.), you need not undergo the same process again when you approach another intermediary."

"No need to issue cheques by investors while subscribing to Equity IPO. Just write the bank account number and sign in the application form to authorise your bank to make payment in case of allotment. No worries for refund as the money remains in investor's account."

A Muthoot M George Enterprise